3- PROJECTS OF ELECTRICAL DEPARTMENT
Due
to the country's urgent need for electricity, has been the development
of this section, which represents the implementation of projects in the
electricity sector is the most important networks and electrical towers
.And below the most important projects implemented :-
A- H.T Overheard Transmission line projects:
item |
Project Name & location |
Beneficiary |
Duration Completed years |
Business type |
1 |
400KV Mosul –Syrian boarder |
E.T.P |
60
days /2002 |
33 Tower
foundation and erection ,5Km Wire Stringing |
2 |
132Kv Beji – Makhol |
E.T.P |
60
days /2002 |
27
Tower foundation and erection , |
3 |
Rehabilitation of Taza- Doz132Kv line |
N.E.T |
45days /2002 |
30
tower & 3 Km. Wire erect. |
4 |
Mosul- Dohuk conection132KV line |
E.T.P |
30
days /2003 |
Foundation and erection of 8 tower |
5 |
Mansur – Yemja – 132kV line Mosul |
E.T.P |
180
days /2004-2005 |
Complete 2 foundation , erection of 101 ,Tower stringing of
30 Km |
6 |
Iraqi –
Turkey
400KV connection line |
E.T.P |
510
days /2005-2006-2007 |
Foundation & erection of 206, tower & stringing of 106 Km
line |
7 |
Mosul
–Erbil – Kirkuk 400KV |
E.T.P |
180
days /2008 |
Erection of 169 tower & 6 , foundation executing |
8 |
Al
Amin – South Baghdad 400KV |
E.T.P |
45
days /2008 |
Stringing of
10 Km |
9 |
Mishraq s/s 132KV connection |
E.T.P |
40
days /2008 |
foundation & erection of 11twoer |
10 |
Samara Diesel –South Tirkrit 132KV |
E.T.P |
45
days /2009 |
foundation & erection of 12 tower |
11 |
Taza-
Beji 400KV |
N.E.T |
30days /2009 |
Stringing of 3.5Km line |
12 |
Abassiya and Hurria Cities double circuit 33kv Line NAJAFF |
Najaff Distribution |
120
days /under execution |
118
tower and 17.7 Km Stringing |
B-132
KV S/S projects for E.T.P
1-New AlMishraq S/S
:
-
Type of
Works : Soil and concrete works of cable trenches and inside roads.
-
Work
duration : 120 days /2008
-
Contract
cost : 700 MID
2-Rehabilitation
of North Beji S/S :
-
Work
duration : 120 days /2008
-
Type of
Works: Complete rehabilitation of transformer and equipments ,
foundation, Control & gear box , building roof and foundation and
walls
-
Work
duration : 45 days /2008
-
Contract
cost : 172 MID
3- Sammurra
Diesel S/S :
-
Type of
Works :Excavation of all trenches and transformers , equipments , soil
and concerting works
-
Work
duration : 150 days /2009
-
Contract
cost : 680 MID
4- North Hilla
S/S :
-
Type of
Works : complete works of control &gear box building execute,
-
Work
duration : 240 days /2009
-
Contract
cost : 1134 MID
5- Khanaqi
Substation S/S :
-
Type of
Works: Soil and wall building, transformer foundation soil & concreting
works, supply and build 6 Site caravans and generator for staff site.
-
Work
duration : 180 days /2009
-
Contract
cost : 835 MID
C-Communication
projects:
1 - Executes
Asia
towers in deferent
mosul
,Kirkuk, tekreet regions including
foundations-erection-painting-fixing of the Communication dishes ,
aerials-generator connection.
2- Executes iraqona towers in deferent
Baghdad
regions
3- Executes atheer towers in deferent of
Babel
regions
D- Supply of Materials & spare parts:
1-
Supply of Mosul Dam Turbine spare parts from Sulzer Brockhardel
France for North Production in 2002.
- Supply of Mosul Dam compressor spare parts from Dropsa Italy for
North Production in 2002
2-MSupply
Mosul Dam White metal from France for North Production in 2002.
3- Supply of Mosul Damp 6Main pumps , Hoses, Seals , from Germany for
controlling dam in 2003
4- Supply of 3000 lighting lanterns from GEM _Turkey for North
distribution in 2002
5 - Supply of 1000 set of Cutout fuse with fusses from Dalman –
Iran for North& Mid distribution in 2002
6 -Supply of Steel bands ( 25 Km), with25000buckless for North
distribution in 2002
7 -Supply of 19 set - 11KV on load
from AREVA _Italy for North distribution in 2009.
8-
Supply of Roller block for ETP, and
north distribution from OMAC _Italy in 2008- 2009.
|