ALAQRM GROUP COMPANIES                                                                

  3-  PROJECTS OF ELECTRICAL DEPARTMENT

 Due to the country's urgent need for electricity, has been the development of this section, which represents the implementation of projects in the electricity sector is the most important networks and electrical towers .And below the most important projects implemented :-

A- H.T Overheard Transmission line projects: 

item

Project Name & location

Beneficiary

Duration Completed years

Business type

1

400KV Mosul –Syrian boarder

E.T.P

60 days /2002

33  Tower foundation and erection ,5Km  Wire Stringing

2

132Kv Beji – Makhol

E.T.P

60 days /2002

27  Tower foundation and erection ,

3

Rehabilitation  of Taza- Doz132Kv line

N.E.T

45days /2002

30 tower   & 3 Km. Wire erect.

4

Mosul- Dohuk conection132KV line

E.T.P

30 days /2003

Foundation and erection of 8 tower

5

Mansur – Yemja – 132kV  line Mosul

E.T.P

180 days /2004-2005

Complete 2  foundation , erection of 101 ,Tower stringing of 30 Km

6

Iraqi – Turkey 400KV   connection  line

E.T.P

510 days /2005-2006-2007

Foundation & erection of 206, tower & stringing of 106 Km line

7

Mosul –Erbil – Kirkuk 400KV

E.T.P

180 days /2008

Erection of  169 tower & 6 , foundation  executing

8

Al Amin – South Baghdad 400KV

E.T.P

45 days /2008

Stringing of 10 Km

9

Mishraq s/s 132KV  connection

E.T.P

40 days /2008

foundation  & erection of 11twoer

10

Samara Diesel –South Tirkrit 132KV

E.T.P

45 days /2009

foundation  & erection of  12 tower

11

Taza- Beji 400KV

N.E.T

30days /2009

Stringing of 3.5Km line

12

Abassiya and Hurria Cities double circuit 33kv Line  NAJAFF

Najaff Distribution

120 days /under execution

118 tower and 17.7 Km Stringing

  B-132 KV  S/S projects for  E.T.P

 1-New AlMishraq S/S :

-         Type of Works : Soil and concrete works of cable trenches and inside roads.

-         Work duration : 120 days  /2008

-         Contract cost : 700 MID

   2-Rehabilitation of North Beji  S/S : 

-         Work duration : 120 days  /2008

-         Type of Works: Complete rehabilitation of transformer and equipments , foundation, Control & gear box , building roof and foundation and walls   

-         Work duration : 45 days  /2008

-         Contract cost : 172  MID

 3- Sammurra Diesel   S/S :

-         Type of Works :Excavation of all trenches  and transformers , equipments , soil and concerting works 

-         Work duration : 150 days  /2009

-         Contract cost : 680  MID

  4- North Hilla    S/S :

-         Type of Works : complete works of control &gear box building  execute,   

-         Work duration : 240 days  /2009

-         Contract cost : 1134  MID

 5- Khanaqi Substation     S/S :

-         Type of Works: Soil and wall building, transformer foundation soil & concreting  works, supply and build   6 Site caravans and generator for staff site.

-         Work duration : 180 days  /2009

-         Contract cost : 835  MID

 C-Communication projects:

 1 -  Executes Asia towers in deferent mosul ,Kirkuk, tekreet  regions  including foundations-erection-painting-fixing of the Communication dishes , aerials-generator connection.

2-  Executes iraqona towers in deferent Baghdad  regions  

3-  Executes atheer towers in deferent of Babel regions

D- Supply of Materials & spare parts:

1-                 Supply of Mosul Dam Turbine spare parts from Sulzer Brockhardel  France  for North Production in 2002.

    - Supply of Mosul Dam compressor  spare parts from Dropsa Italy  for North Production in 2002

  2-MSupply  Mosul Dam  White metal  from France  for North Production in 2002.

3-  Supply of Mosul Damp 6Main pumps , Hoses, Seals , from  Germany for controlling dam   in 2003

4- Supply of 3000 lighting lanterns   from GEM  _Turkey   for North distribution  in 2002

5 - Supply of 1000 set  of Cutout fuse  with fusses    from Dalman – Iran    for North& Mid  distribution  in 2002

6 -Supply of Steel bands ( 25 Km), with25000buckless  for North distribution  in 2002

 7 -Supply of 19 set -  11KV  on load    from AREVA  _Italy   for North distribution  in 2009.

8-  Supply of Roller block for ETP, and north distribution   from OMAC  _Italy  in 2008- 2009.